Motivation

Islands exhibit distinct structural and operational constraints in their transition towards decarbonized energy systems. Their geographic isolation often necessitates a high dependency on imported fossil fuels, resulting in elevated energy costs, heightened vulnerability to supply disruptions, and increased greenhouse gas (GHG) emissions. Although renewable energy sources (RES), particularly wind and solar, represent viable and sustainable alternatives, their deployment in insular environments is hindered by constraints such as limited land availability, pronounced variability in generation profiles, and the absence of extensive energy infrastructure typically available in continental systems. Moreover, the inherently intermittent nature of RES poses significant challenges for maintaining grid reliability and operational stability in the absence of advanced energy storage and management frameworks. Therefore, achieving complete decarbonization mandates not only the substitution of conventional generation assets with renewables but also the holistic optimization of system architecture — encompassing accurate sizing of infrastructure components — to effectively align energy demand, storage capabilities, and renewable generation potential.

Objectives

To address the aforementioned challenges, this study employs a linear programming–based optimization framework to determine the optimal configuration of Distributed Energy Resources (DER) and Renewable Energy Systems (RES). The design of an efficient and sustainable energy infrastructure constitutes a high-dimensional and multi-criteria problem, requiring the simultaneous consideration of interrelated variables such as capital and operational expenditures, spatial constraints, resource availability, load profiles, and technical limitations. The inherent complexity and interdependence of these factors render manual evaluation approaches infeasible, thereby necessitating the application of advanced mathematical modeling and computational optimization techniques to derive cost-effective and technically viable solutions. The proposed optimization methodology is subsequently applied to a set of case studies, with a particular focus on the island of Borkum (Germany). Through the simulation and comparative analysis of multiple deployment scenarios, the study generates quantitative evidence and strategic insights regarding the integration of RES in insular contexts. The results aim to validate the effectiveness of the proposed approach and to inform decision-making processes related to the design, scalability, and long-term sustainability of decarbonized energy systems for island communities.

Literature review

The optimization of renewable energy resource deployment has become a pivotal area of research, particularly within islanded energy systems where supply security, reliability, and cost-effectiveness are significantly constrained. This literature review provides a structured synthesis of the most influential contributions in the domain, with an emphasis on linear programming–based optimization approaches, the design and operational control of microgrids, integration strategies for energy storage systems, and empirical case studies that illustrate the technical and economic feasibility of achieving high renewable energy penetration in insular contexts.

Optimization for renewable energy allocation

1 establishes a significant precedent in “Optimization for Renewable Energy Resource Allocation Using Linear Programming: A Case Study”, where linear programming techniques are applied to optimize the allocation of a limited budget (500.000€) across various renewable energy projects. The study "Optimizing Design and Dispatch of a Renewable Energy System"2 advances methodological complexity by presenting a mixed-integer programming model that prescribes optimal combinations of renewable technologies, conventional generation, and storage systems, including combined heat and power systems. This model prioritizes the minimization of fixed and operational costs while ensuring system interoperability and reliability2.

Applications in Island environments

The research "Renewable Energy Communities in Islands: A Maltese Case Study" offers a valuable perspective on the implementation of renewable energy communities (RECs) in Malta's low-voltage distribution network. This study, through the analysis of five cases, demonstrates how centralized community storage can significantly improve self-sufficiency, reduce peak electricity demand, and minimize reverse power flows into the utility grid3.

The work "Linear Programming Approach Based Demand Response to Support Intermittent and Non-Dispatchable Renewable Energies Penetration in Nusa Penida Iconic Island" evaluates the potential penetration of renewable sources in the Cyclades, a complex of Greek islands. This study highlights the importance of hydrogen as an energy vector to increase the participation of renewable and intermittent sources in the energy supply, suggesting the possibility of achieving 100% renewable supply for island communities4.

The research "Research on Energy Storage Optimization Operation Schedule in an Islanded Power System with High Renewable Energy Penetration" focuses on Taiwan's Kinmen Island, studying scheduling systems for renewable energy penetration with the aim of reducing accidents in the electrical system. The study emphasizes the importance of full participation of power system stabilizers in reserve scheduling to handle unexpected situations and load changes5.

Case study design

Problem description

The primary objective of the sizing algorithm is to identify the optimal configuration of energy generation and storage assets that satisfies the projected energy demand of a given site, while minimizing the total system cost, including both capital and operational expenditures. The algorithm operates on a predefined set of candidate technologies, provided as input parameters, which encompass onshore and offshore wind turbines, photovoltaic (PV) installations, prosumer systems (capable of both energy generation and storage), lithium-ion and hydrogen-based energy storage systems, interconnection capacities, and electric vehicle (EV) charging infrastructure.

Mathematical model

The algorithm is formulated as a modular optimization model based on Linear Programming (LP). The dimensionality of the model—i.e., the number of decision variables and constraints—adapts dynamically according to the set of technologies selected for deployment. Its modular architecture allows for the selective activation or deactivation of entire technology blocks (modules), enabling flexible configuration beyond simple parameter tuning. Each module encapsulates its own constraints and cost formulations, contributing to the overall objective function and system behaviour. The LP-based model is applied to key infrastructure components such as wind turbines (onshore and offshore), energy storage systems (lithium-ion and hydrogen), electrical interconnections, prosumer units, and photovoltaic systems. A separate optimization module is used for electric vehicle (EV) infrastructure, and its resulting outputs—primarily cost metrics—are integrated into the cost function of the main model to ensure holistic system-level optimization.

Cost expressions (Cost function) are very typical of LP optimization, used in many problems in which expenses are being minimized, including energy hubs models6,7.

The installation costs multiply the sizing variables, whereas the O&M costs multiply the sum of all the energy either generated or flowing through the module.

This formula is structured as follows:

∑modulescinst⋅P+∑modules(cO&M⋅P)(1)

Where P is the sizing variable of each installation (generally a power value [kW]).

In addition to the cost function, there is a similar approach for a constraint at a general level (for all the modules): there is an expression that is the difference between the expected consumption and the sum of the total installed power between all the elements. The objective of the restriction is to reduce this difference to 0.

C=C−∑modulesPinstalled<10−3(2)

where

C → Consumption expression

Pinstalled → Installed power

All the modules have information about costs and space limitations that are used in the model constraints. For example, in the case of the onshore turbines: The installed power, that is computed through the product of a generation coefficient and the wind speed, should be greater than what exists initially:

P0onshore≤Ponshore(3)

The space occupied by turbines should be lower than available:

Sonshore⋅(Ponshore−P0onshore)≤STonshore(4)

Sonshore → Onshore installation space

STonshore → Total onshore space

Ponshore → Onshore installed power

P0onshore → Initial onshore installed power

In the case of the solar parks, the generation is calculated using the irradiance and the guaranteed minimum performance. The space limitation, like in the case of the turbines, is related to the initial installed power in the lower bound and to the available space in the upper. The prosumers, in addition to the space limitations, include other restrictions like the battery capacity:

Ebattery≥E0prosumer−ϵprosumer⋅∑0t+1Eprosumer[t](5)

Ebattery → Battery capacity

E0prosumer → Prosumer initial stored energy

ϵprosumer → Battery prosumer efficiency

Eprosumer → Prosumer net energy

Or the energy flow (the energy leaving should be less than that entering):

ϵprosumer⋅Eprosumer[t]≤E0prosumer−ϵprosumer⋅∑0t+1Eprosumer[t](6)

Similar expressions appear for lithium batteries, regarding the battery capacity:

Elithiumcap≥E0lithium−ϵlithium⋅∑0t+1Elithium[t](7)

Elithiumcap → Lithium battery capacity

E0lithium → Lithium initial stored energy

ϵlithium → Lithium battery efficiency

Elithium → Lithium battery net energy

The charging and discharging power limits:

Pminlithium<Elithium[t]/h_p_t<Pmaxlithium(8)

Or the energy flow:

ϵlithium⋅Elithium[t]≤E0lithium−ϵlithium⋅∑0tElithium[t](9)

Hydrogen batteries have very similar expressions, also regarding space constraints, battery capacity and charging limits.

Interconnexions are part of the complete installation, and there are two different modules for them: the existing ones, that have power limitation

−Secable<Eeconn[t]/h_p_t<Secable(10)

Secable → Size of existing cable

Eeconn → Energy net of existing connection

and the new ones, for which there are also power restrictions:

Upper bound:

Enew[t]/h_p_t≤Sncable⋅In(11)

Enew → New interconnection net energy

Sncable → Size of new cable

In → New installed interconnections

Lower bound:

Enew[t]/h_p_t≥−Sncable⋅In(12)

As commented before, there is an additional module that computes the costs and contributions to the consumption expression from the electrical vehicles. The restrictions related to this part of the installation are the following: The number of charging vehicles is lower than the number of slow and fast charging stations:

cpertour[t]⋅vehtour[t]+cperurban[t]⋅vehurban[t]+cperinhab[t]⋅cperveh⋅vehinhab[t]≤csslowactive[t]+csfasttotal[t](13)

cpertour → ev_tourists_charging_percentage

vehtour → ev_tourists_vehicles

cperurban → ev_urban_services_charging_percentage

vehurban → ev_urban_services_vehicles

cpertour → ev_tourists_charging_percentage

cperinhab → ev_inhabitants_charging_percentage

cperveh → ev_tourists_charging_percentage

vehinhab → ev_urban_services_vehicles

The number of slow and fast charging stations Is lower than the total of each kind:

csslowactive[t]≤csslowtotal(14)

csslowactive → ev_active_slow_charge_stations

csslowtotal → ev_total_slow_charge_stations

csfastactive[t]≤csfasttotal(15)

csfastactive → ev_active_fast_charge_stations

csfasttotal → ev_total_fast_charge_stations

Space limitation for charging stations:

csslowtotal⋅csslowspace+csfasttotal⋅csfastspace<=cstotalspace(16)

csslowspace → ev_slow_charge_station_installation_space

csfastspace → ev_fast_charge_station_installation_space

cstotalspace → ev_total_charging_station_space

The number of charging stations installed should be greater than the initial number:

Pslowinstalled≤csslowtotal(17)

Pslowinstalled → ev_already_installed_slow_charge_power

Pfastinstalled≤csfasttotal(18)

Pfastinstalled → ev_already_installed_fast_charge_power

The sum of the objective function corresponding to electric vehicles considers the installation and maintenance cost of the slow and fast charging stations:

ICslow⋅(csslowtotal−Pslowinstalled)+ICfast⋅(csfasttotal−Pfastinstalled)+MCslow⋅Pmaxslow⋅⋅∑csslowactive+MCfast⋅Pmaxfast⋅∑csfastactive(19)

ICslow → Slow charge station installation cost

ICfast → Fast charge station installation cost

MCslow → Slow charge station maintenance cost

MCfast → Fast charge station maintenance cost

Data

Environmental variables such as ambient temperature, solar irradiance, and wind speed constitute key input parameters for estimating the energy output of the various generation technologies integrated into the system. In parallel, energy demand profiles are incorporated as critical boundary conditions within the optimization framework, influencing the sizing and dispatch strategy of installed capacity8.

Each technological component within the system requires detailed techno-economic data, including capital expenditure (CAPEX), operational and maintenance costs (OPEX), spatial footprint per unit, and constraints related to the total area available for deployment.

Furthermore, the electric vehicle (EV) infrastructure module integrates additional socioeconomic and behavioural parameters, such as local population density, fleet size of urban service vehicles, and the proportion of time these vehicles are operated under active charging conditions. These variables collectively inform the estimation of EV-related energy demand and infrastructure requirements within the overall system model.

Results and discussion

his section aims to assess the performance and applicability of the proposed linear programming–based optimization algorithm for the design of an energy infrastructure tailored to insular environments. The specific characteristics of the selected use case—namely, limited land availability and strategic commitment to renewable energy integration—position the island as an optimal testbed for evaluating advanced energy system design methodologies. The following subsections outline the scenario definition, including the technical assumptions, boundary conditions, and input parameters used for modelling the case of Borkum Island. Results are then presented and discussed, covering the evaluated deployment scenarios, key performance indicators (KPIs), and the broader implications for the island’s energy transition pathway. This case study focuses on Borkum, the westernmost and largest of Germany’s East Frisian Islands, encompassing approximately 31 km2. Located roughly 20 miles off the German mainland, Borkum represents the country’s northwesternmost territory and serves as a representative example of a geographically constrained yet strategically positioned energy system8.

Borkum has a resident population of approximately 5,500 inhabitants, primarily concentrated in its sole urban settlement, also named Borkum. However, during peak tourist seasons, the island’s population increases significantly, exceeding 25,000 individuals. The island’s climate is predominantly influenced by the North Atlantic polar front throughout the year, resulting in variable and frequently overcast weather conditions. Summer temperatures tend to be lower than continental averages due to the moderating effect of oceanic currents, while winters are comparatively mild, though often accompanied by strong winds and persistent cloud cover. Climatic data for the year 2019—including ambient temperature, solar irradiance, and wind speed—has been used as the basis for energy generation modelling. In that same year, the island's total annual electricity demand was 30.6 GWh. The installed generation capacity on Borkum produced a total of 14.74 GWh annually. Of this, approximately 10.6 GWh was generated by two wind turbines rated at 1.8 MW each, while a 1.4 MW central photovoltaic (PV) installation contributed 1.24 GWh, and distributed rooftop PV systems—primarily deployed under the NETfficient project—generated an additional 0.27 GWh. Supplementary electricity generation is provided by a gas-fired Combined Heat and Power (CHP) plant, supplying over 2.9 GWh per year. Regarding thermal energy, annual heating demand is estimated at approximately 130 GWh, currently met through a combination of the gas CHP system and individual natural gas boilers. Due to the deficit between local generation and consumption, the island imports approximately 17.06 GWh of electricity annually from the mainland. Interestingly, despite the negative net balance, approximately 1.2 GWh is exported back to the mainland. This is attributed to the temporal mismatch between renewable energy production and local consumption—specifically, surplus generation during peak production periods that exceeds local demand is fed into the external grid.

Assumptions

A total of ten (10) scenarios were developed for Borkum using different facilities and comparing with the facilities already installed in Borkum (base example). Some assumptions were considered in advance prior to generating each scenario.

Assumption 1. Price-related assumptions

Table 1 provides the cost ratios related to the different facilities and energy parameters that have been considered in the examples developed:

Table 1. Facilities and energy cost ratios.

Cost RatioValue
Energy from mainland100 €/MWh
PV facilities supply and installation600 €/kWp
Batteries supply and installation300 €/kWh
Wind turbine1200 €/kW
Hydrogen storage700 €/kWh
Electrolyzer650 €/kW
Fuel cell1700 €/kW

The cost ratios of H2 storage facilities (Electrolyzer and Fuel Cell) described in Table 2 have been obtained from the literature where Levelized Cost of Storage (LCOS) for a hydrogen system is analyzed and researched. The cost ratio of Hydrogen Storage has been obtained based on the costs included in the Grant Agreement subtracting the prices of electrolyzer, Fuel Cell and Buffer Battery.

Table 2. Equipments cost ratios.

EquipmentRatioSizeCost
minmaxunitsminmaxunits
Electrolyzer650€/kW515kW32509750€
Fuel cell1700€/kW515kW850025500€
Battery Buffer300€/kWh510kWh15003000€
TOTAL1325038250€

Considering the price of the H2 storage system considered (495.000,00 €) and the size range of the H2 storage tank, the price range for the storage results as describe in Table 3:

Table 3. H2 storage tank price.

EquipmentPrice (€)Size (kg)Cost (€/kWh)
minmaxminmaxminmax
H2 storage tank456.750481.750520685,192.890,79

A 700,00 €/kWh ratio has been considered for the H2 storage tank.

No Maintenance nor operation costs have been considered for any renewable technology. In addition, no monetary compensation is obtained for the energy fed into the grid.

Assumption 2. Return of Investment Assumptions

Another assumption considered is the Return of Investment (ROI) period. There has been considered a period of 10 years, and has been considered by dividing the costs of supply and installation of the facilities stated previously by 10. Consumption, temperature and wind speed data have been provided by NBG partner and included in data.csv input file.

Irradiance data has been obtained from PVGIS for a horizontal plane and a typical year9.

No limitations of space have been considered.

Assumption 3. Efficiencies assumptions

The following efficiencies have been considered:

  • PV plant and Prosumers:

    • Performance Ratio: 75%

  • Batteries:

    • Efficiency: 100%

  • Wind Turbines:

    • Minimum Wind: 5,0 m/s

    • Optimal Wind: 18,9 m/s

    • Maximum Wind: 34,0 m/s

  • H2 Storage:

    • Electrolyzer efficiency: 45%

    • Fuel Cell efficiency: 65%

4. Total Energy Consumption Assumptions

A total of 32,62 GWh consumption will be considered for all scenarios.

Results comparison between configurations

Scenario 1: Consider just the facilities already installed in Borkum:

  • One PV Plant of 1,4 MWp.

  • One set of prosumers with an installed power of 0,27 MWp.

  • Two wind turbines of 1,8 MW each.

The objective function reflects the cost of energy from the mainland.

Scenario 2: PV optimization has been calculated with the base example data and optimizing the use of PV plants

Scenario 3: Wind Turbine Optimization. Using data considered and optimizing the use of Wind Turbines.

Scenario 4: Batteries Optimization. First trial with the pieces of the batteries initially considered has been performed, returning no battery should be installed that means the benefits of the battery (less energy from and to mainland) do not compensate the cost of the battery.

Scenario 5: Batteries Optimization. Second trial with the pieces of the same batteries as scenario 4 but with one tenth of the initial cost for the batteries (30 €/kWh).

Scenario 6: H2 storage optimization. First trial with the pieces of H2 initially considered has been calculated, returning no equipment should be installed to optimize the function cost, similar to scenario 4.

Scenario 7: Second H2 storage optimization with also one tenth of the initial cost of H2 storage has also been calculated, but it also does not propose the installation of any equipment.

Scenario 8: PV optimization with batteries: PV plant optimized combined with Battery Optimization. One tenth of the initial cost for the batteries has been considered.

Scenario 9: Wind Turbine Optimization, also with batteries consideration (one tenth of battery costs).

Scenario 10: PV and Wind Turbine Optimization, with also usage of batteries (Considered one tenth of the initial cost of the batteries.

Table 4 summarizes scenarios results:

Table 4. Scenarios results summary.

ScenariosEnergy (GWh)Cost (k€)
ImportExportPV, prosumersWind TurbinesImportPV, prosumersWind TurbinesBatteriesTotal
1Base23,040,141,548,182303---2303
2PV of 7747 kWp16,620,858,678,181662465--2127
33 Wind Turbines
1800 kW each
16,1931,5417,91619-513-2131
4No equipment---------
5Batteries of 1323 kWh22,090,081,548,182299--42302
6No equipment---------
7No equipment---------
8PV plant of 14.826 KWp10,160,9115,188,181016890-821988
Batteries of 27.311 kWh
93 additional Wind Turbines
1.800 kW each
14,563,251,5419,771456-640312127
Batteries of 10.284 kWh
102 additional Wind Turbines
1.800 kW each
8,561,7213,212,58856760233881937
PV plant of 12.667 kWp
Batteries of 29.467 kWh

The application of the linear programming–based optimization algorithm across multiple deployment scenarios yields valuable insights into the most cost-effective and technically viable configurations for energy generation, with a particular focus on maximizing renewable energy integration and minimizing dependence on external supply. The baseline scenario, which reflects the existing infrastructure on Borkum, exhibits a higher dependency on electricity imports from the mainland, resulting in elevated operational costs. Scenarios incorporating additional renewable energy sources (RES) demonstrate a significant reduction in import requirements and, in some cases, a net energy export, thereby enhancing local energy autonomy. The degree of cost reduction is strongly influenced by the specific mix and installed capacity of the selected technologies. Scenarios integrating photovoltaic (PV) systems and wind turbines exhibit a pronounced shift toward local generation, contributing to both increased self-sufficiency and decreased levelized energy costs. Notably, scenario 3, which includes the deployment of additional wind turbines, further mitigates external energy reliance. The inclusion of battery energy storage systems (BESS) enhances the temporal alignment between renewable generation and demand, improving grid stability and the overall utilization of locally produced energy. While scenarios that integrate storage solutions exhibit further reductions in energy imports, the economic viability is highly sensitive to the high capital expenditures associated with battery systems. The cost-effectiveness of such investments must be justified by the corresponding reduction in imported energy volumes and peak shaving benefits.

Among the configurations evaluated, scenario 10—characterized by the simultaneous deployment of utility-scale PV, additional wind turbines, and battery storage—achieves the highest reduction in dependency on mainland imports while maintaining a balanced cost-performance profile. The results suggest that the optimal trade-off between energy independence and investment cost is attained through a diversified portfolio of renewable generation technologies complemented by storage capacity.

Ethics and consent

Ethical approval and consent were not required

Contribution

The proposed solution is intended to serve as a pre-sizing and decision-support tool for follower islands seeking to evaluate and adapt energy system configurations aligned with the ISLANDER framework. The tool enables users to perform techno-economic optimization analyses, the outputs of which provide a foundational design reference for the tailored deployment of energy technologies in diverse insular contexts. Users are required to supply a structured input dataset representative of a full typical meteorological year (TMY), including all relevant techno-environmental and demand-side parameters associated with the candidate technologies to be considered in the optimization process. Furthermore, users must define and parameterize the specific characteristics (e.g., technical performance, costs, spatial constraints) of each technology selected for inclusion in the analysis. By executing multiple simulation scenarios, the tool allows comparative assessments of alternative technology mixes and system configurations. This facilitates the identification of optimal solutions in terms of cost efficiency, energy autonomy, and environmental performance, thereby supporting evidence-based decision-making for the energy transition of follower islands.

Conclusions

This article presents the implementation and application of a linear programming–based software tool developed for the optimal sizing of energy systems, with a focus on scenario-based analysis and interpretation of the resulting outputs. The tool is designed to support energy system planners and decision-makers in identifying the most cost-effective technological configurations for the decarbonization of islanded or geographically isolated energy systems. It accounts for both capital investment and operation and maintenance (O&M) costs, thereby facilitating informed decision-making during the early-stage design and planning phases. By simulating and analyzing multiple deployment scenarios, the tool generates quantitative insights that are critical for the techno-economic optimization of distributed energy systems in insular contexts. Key conclusions derived from the scenario analyses include:

Overall, the tool provides a robust analytical framework for exploring decarbonization pathways in isolated energy systems, offering a data-driven foundation for strategic infrastructure planning and investment.

Limitations and future work

While the current version of the software fulfills the core functional requirements, there are several opportunities for enhancement that could be incorporated into future iterations to improve analytical depth, user experience, and decision-support capabilities for energy system planners.

From a usability standpoint, improvements to the graphical user interface (GUI) could enhance interaction efficiency and accessibility. Minor interface refinements, such as the integration of a target Return on Investment (ROI) parameter within both the computational model and the visualization layer, would increase transparency and facilitate financial assessment. Furthermore, the current version lacks the capability to simulate the full duration of the ROI period—a critical feature that could be implemented to support long-term investment evaluation. Enhanced output visualizations, such as detailed energy production profiles, cumulative performance indicators (e.g., totalized energy flows), and a comprehensive energy dashboard, would offer greater insight beyond system sizing metrics. Additional temporal analysis functionalities, including disaggregation of results by month or intraday intervals, as well as scenario comparison tools, would significantly broaden the scope of strategic analysis.

In terms of system modelling, several functional extensions are proposed. These include the incorporation of thermal energy generation systems, the enforcement of energy storage boundary conditions (e.g., ensuring battery and hydrogen tank state of charge (SOC) equivalence at the start and end of simulation periods), and the inclusion of SOC degradation dynamics over time. Moreover, the optimization framework could be expanded to accommodate energy export transactions, thereby introducing a revenue stream component and enhancing the financial realism of the simulations. Cost modelling could also be refined by incorporating dynamic grid electricity pricing and energy export tariffs. Maintenance cost estimation could be improved by introducing a more granular methodology that accounts not only for energy throughput but also for system capacity and operational cycles. Furthermore, the adoption of advanced financial metrics—such as Levelized Cost of Ownership (LCO)—would enable a more comprehensive assessment of system lifecycle economics, facilitating robust techno-economic comparisons across alternative configurations.

Data availability

The datasets generated and analysed in this study are openly available in DOI: https://doi.org/10.23728/b2share.4a96fdc741d54ea285eda021df4139338.

The repository includes:

  • Input datasets used for the linear programming optimization (typical meteorological year data, load profiles, and techno-economic parameters for photovoltaic, wind, storage, and electric vehicle infrastructure).

  • Scenario configuration files and model parameters used to reproduce the results.

  • Output data generated by the simulations, including energy balances, cost calculations, and performance indicators.

No restrictions apply to the use of these data.

Data are available under the terms of the Creative Commons Attribution 4.0 International license (CC-BY 4.0).

References

  • 1.  Ghabban MO, Marzouq AH, Alsughayyir YA, et al.: Optimization for renewable energy resource allocation using linear programming (a case study). Academic Journal of Research and Scientific Publishing. 2024; 18. Publisher Full Text
  • 2.  Ogunmodede O, Anderson K, Cutler D, et al.: Optimizing design and dispatch of a renewable energy system. Appl Energy. 2021; 287: 116527. Publisher Full Text
  • 3.  Micallef A, Staines CS, Licari J: Renewable energy communities in Islands: a maltese case study. Energies. 2022; 15(24): 9518. Publisher Full Text
  • 4.  Nurhayati G, Sasmono S, Hariyanto N: Linear programming approach based demand response to support intermittent and non-disptachable renewable energies penetration in Nusa Penida Iconic Island. 2023; 648–653. Publisher Full Text
  • 5.  Chen YT, Kuo CC, Jhan JZ: Research on energy storage optimization operation schedule in an Island system. Appl Sci. 2011.
  • 6.  Geidl M, Andersson G: Optimal coupling of energy infrastructures. IEEE, 2007. Publisher Full Text
  • 7.  del Real AJ, Arce A: Optimization strategy for element sizing in hybrid power systems. Journal of Power Sources. 2008.
  • 8.  González Naranjo A: Borkum Island environmental and energy input data. s.l.: -EUDAT-, 2024. http://www.doi.org/10.23728/b2share.4a96fdc741d54ea285eda021df413933
  • 9.  European Comission: Photovoltaic geographical information system. 2024. Reference Source